Crews constructed a new distribution substation to service Presque Isle Electric and Gas on a greenfield site, requiring installation of a new 138kV circuit breaker, 5MVA transformer, low side distribution bus including voltage regulators, metering transformers, relay transformers, 2 circuit exits and a capacitor bank. This project will also include a control building, distribution H-Frame and static mast.